Hooke Park Time Schedule

Day 1 - Tuesday
-Setup files for CNC.
-Sort out pieces for moulding for CNC

Day 2 – Wednesday
-Cut out 24mm into pieces for CNC or maybe for frame column

Day 3 – Thursday
CNC first 5 layers of Mould 1

Day 4 – Friday
-Laminating Mould 1
-CNC Mould 2

Day 5 – Saturday
-Setting up plaster and layer fiber glass for mould 1 then wait to dry
-Laminating Mould 2
-Keep layering and wait to dry
Day 6 – Sunday
Day 7 – Monday
-Layering Mould 2 with plaster and fiber glass
-Wait to dry
-Sanding and trimming column from mould 1
Day 8 – Tuesday
-Assembling Columns from Mould 1 and 2 together
-Fixing edges and gluing

Day 9 –Wednesday
-Same thing

Post a comment

(If you haven't left a comment here before, you may need to be approved by the site owner before your comment will appear. Until then, it won't appear on the entry. Thanks for waiting.)

About

This page contains a single entry from the blog posted on March 13, 2007 11:54 AM.

The previous post in this blog was Hooke Park Proposal.

The next post in this blog is Modelling the Entire Site.

Many more can be found on the main index page or by looking through the archives.

Powered by Movable Type 3.32
Hosted by LivingDot