Hooke Schedule

Hooke Schedule

○1Prototype_01 (laminated plywood) / 2 way folding
○2Prototype_02 (aluminum) / 3 way folding

13Mar(tue) / day_1

Arriving

14Mar(wed) / day_2

-○1Curving Test (3 angles, 86.00 / 38.00 / 90.00 ) with laminated ply
-○1Curving Test-2 / glued joint test
-○1CNC preparation (perforation test-1)
-○1○2Making Base Form……

-Material’s arriving (1.5mm ply 1.5msq * 4)

-Order extra material (1.5mm ply * ? / super glue gel )

-Confirm schedule with Nathasha

15Mar(Thu) / day_3

-○1CNC cutting (perforation)
-Confirm Final Design
-○1○2Making zig for specific curve (from previous day test)

16Mar(Fri) / day_4

-Material’s arriving (1.5mm aluminum sheet 2m×1m*4)
-○2cutting sheet (all day)

*decide for final output (with time schedule) whether ply or alum.

17Mar(Sat) / day_5

-○2Curving Test (3 angles, 86.00 / 38.00 / 90.00 ) with laminated aluminum
-○2Curving Test-2 / glued joint test
-○2Riveting

18Mar(Sun) / day_6

-○1CNC preparation (for all the components)

19Mar(Mon) / day_7

Working day (curving, laminating, assembling into one )

20Mar(Tue) / day_8

Working day

21Mar(Wed) / day_9

Working day

22Mar(Thu) / day_10

?

23Mar(Fri) / day_11

Leave Hooke Park

About

This page contains a single entry from the blog posted on March 14, 2007 1:26 AM.

The previous post in this blog was Hooke proposal.

The next post in this blog is Work in Progress.

Many more can be found on the main index page or by looking through the archives.

Powered by Movable Type 3.32
Hosted by LivingDot